Monday, October 15, 2012

Concrete Caps Add Finishing Touch

The mason returned Monday to place the pre-cast concrete caps on the new east wall. We are really pleased with the results!
 The caps were created to replicate the color of the limestone accents.
 The shape of the cap slopes slightly to help shed water.
The mason will return on Tuesday to do some final touch-ups. 

Stay Tuned for Our Next Adventure!

Drywall: Day 3

The drywall crew kept up a great pace on Saturday, and finally left noTTafarm just after dark. They continued today, and will finish hanging wall board in the kitchen and pantry tomorrow (Tuesday) then make way for the tapers and the mudders.
Is there a messier element in new construction? 
I wish they would accidentally leave their scaffolding behind so that I can stain those windows way up on the great room wall. Oh, and for painting  . . . someone has to climb up there to paint the wall.
After work on Monday, Leo checked out the progress and seemed intrigued by the waste pile in the great room. 
Remember when I always made Scott stand in the future laundry closet
Now that the drywall is done, it's looking pretty good!
Stay Tuned for More Progress!

Saturday, October 13, 2012

"New People" Welcome New Baby!

Congratulations, Kevin and Sara!
The lovely couple that purchased our Grant Street house a year ago welcomed their first baby this morning. Their son, Bennett Spalding, was born at 6:20 a.m., weighing 6 lbs. 2 oz. and measuring 18 inches long.

Snug-As-Bugs with Room to Spare

With storms predicted to rumble over noTTafarm Friday evening, and with the concrete cured sufficiently, Scott agreed that we could park our cars in the garage for the first time. It was quite exciting to pull the Mini, the Escape, and Scott's prized Audi into their respective spots.
Pretty Cool!
Stay Tuned for More Progress!

Talkin' 'bout Walls

The progress this week at noTTafarm was highlighted by the completion of interior insulation and the beginning of drywall installation. Sound-absorbing insulation was added between interior walls above ceilings which should cut down on the clomping factor (a tell-tale sign that a member of the Ward side of the family (including me) is in the house.) The rooms definitely felt more cozy and quiet with the insulation complete!
By Friday (October 12) morning, the insulation was covered with its vapor barrier and ready for drywall.
A view of the insulated casual dining area ceiling.
 The drywall was delivered at about 7:30 Friday morning. 
After some discussion with Scott, it was decided that the first batch should be delivered to the second story through the deck door in the master bedroom. They used their big boom truck to lift the stack of sheets up and over the deck.
Each piece was moved by hand into the house. I left for work shortly after this photo was taken but Scott tells me that the first floor drywall was delivered through the south patio doors. They used the boom to lift it over our new patio.
The drywall crew made great progress on Friday. 
By the time we got home from work, most of the great room and other first floor spaces were nearly complete.
The master bedroom really feels cozy now that the walls are in place.

The drywall work continues today (Saturday the 13th) as the crew arrived at about 8:15 for a full day of work. They should be able to begin taping and mudding on Monday.
Stay Tuned for Our Next Adventure!

Sunday, October 7, 2012

Bathroom Tile Progress Moves to the Floor

Scott made great progress in the 1920 bathroom this weekend! The majority of the floor tile is now in place, and it looks great. 
Check it out!
He started on Saturday by placing the tile inside the shower stall. He had to make sure the little mosaics would fit nicely around the drain. Once that difficult spot was done, he moved on to the field tile.
Each 1 ft. x 1 ft. mesh-backed piece is comprised of 144 individual hexagon tiles. It's a good thing someone figured out how to do that whole mesh-back thing! I can't imagine trying to precisely place each tile. I teased Scott about how long he took to place each piece but he just wants it to be correct! (So I can't fault him for that, now can I?)
Due to the nature of the hexagon shape, the perimeter of the floor will need to be completed with half-pieces of tile. Luckily, Scott got to buy a new tool - a pair of tile nippers - to help with the task. He will tackle this process during the week.
The field tile is all in place! Now all we need is a piece of granite or marble to serve as a shower threshold, and the aforementioned half-pieces. Scott hopes to have everything in place and ready to grout next weekend.
Stay Tuned for Our Next Adventure!

2 Days + 3 Truckloads = 1 Big Driveway

The T. Hurt crew set up shop here at noTTafarm on Friday to pour, color, and stamp the new southside patio. Thursday afternoon, they finished laying out a grid of reinforcing rebar and the wood forms.
Friday morning, the forms were set and the patio was ready for concrete.
By the time I arrived home from work Friday afternoon, we had one beautiful patio! Of course, Bibbers was the first to enjoy it. (Luckily, the concrete was too far along to have permanent Bibbers prints embedded.)
We chose to have the patio stamped in a random pattern, and colored a darker, slate gray. Pretty spiffy!
 Also on Friday, a step off of the northwest stoop was framed and readied for concrete.
A lot of thought went into the layout of the driveway before the grading began. The crew worked most of Friday to get it ready for concrete.
Bright & shiny (7:45) Saturday morning, the crew arrived. 
Three truckloads of concrete were used throughout the day.
Getting started
Temps were chilly this weekend! The high on Saturday was about 53 but the sunshine kept the mood upbeat.
Wonder where I could get a pair of those yellow boots...pretty cute!
Jarek (orange shirt) worked on-site until well after dark, leaving at around 9PM Saturday. After the concrete was poured, he worked a lot at grading the entire job site with the Bobcat. The surplus dirt that was piled on the east side of the barn when the basement was dug has been reduced by about two-thirds, and our backyard now looks more like an actual yard and not a waste site for lumber odds-and-ends.
Thank you, Jarek!
By 10 o'clock, the third load of concrete had arrived and the work continued down the slope. The existing concrete was sliced to create a nice, clean edge for the new concrete to abut.
This may seem like a large area of concrete but think of the rollerskating I could do! Scott even suggested getting a basketball hoop.
By 12:45 Saturday, the concrete was all in place, including along the courtyard wall. Later in the afternoon, Jarek scored the driveway to create expansion joints. Now we just have to wait the prescribed seven days before we can drive on the new concrete and park in the garage!
 Saturday afternoon, the step off the northwest stoop was created. 
Also on Saturday, expansion joints were cut into the patio. They also rinsed the patio to reveal more of the depth of desired color before covering the whole thing with a tarp for curing.
All in All, A Pretty Great Effort by the Concrete Guys!
Stay Tuned for Our Next Adventure!
Drywall on Wednesday (?!)